Project update – May 2024
Work on Crowchild Trail N.W. begins in early June. Reduced speeds and temporary lane closures will be in effect during construction. Crews will work overnight and on weekends to minimize disruptions.
However, motorists are advised to expect delays. Please watch for crews and follow posted signage. The work is anticipated to be completed by September 2024.
Tentative construction timelines
June – July
- Milling and paving Westbound and Eastbound Crowchild Trail N.W. from Brisebois Drive N.W. to Stoney Trail N.W.
- Concrete rehabilitation of on- and off- ramps along Crowchild Trail N.W.
July 4 – July 10
- Construction shutdown during Calgary Stampede
July – September
- Concrete rehabilitation and paving on Westbound and Eastbound Crowchild Trail N.W. from Brisebois Drive N.W. to Stoney Trail N.W.
- Milling and paving of on- and off-ramps along Crowchild Trail N.W.
- Milling and paving intersection of Crowchild Trail N.W. and 5 Avenue N.W. Stampede Stoppage Notice: There will be a 10-day break in construction from July 5 to July 14 for Crowchild Trail N.W. to operate at regular speeds during the Calgary Stampede.
Note: Road construction timelines are dependent on several factors (e.g. weather, site conditions, materials availability) and are subject to change.
Impacts on traffic and area
We recognize that this work may cause some inconvenience to your community, and we are committed to minimizing these impacts.
- Lane closures: 1-2 lanes will remain open. Please follow posted road signs. Daytime and overnight lane closures will be in effect with advance notice provided.
- Daytime Work: Concrete replacement from 9 a.m. to 3 p.m., on both weekdays and weekends.
- Nighttime Work: Milling and paving from 9 p.m. to 5 a.m. on weekdays and from 9 p.m. to 8 a.m. on weekends.
- Noise and Vibrations: Residents may experience construction noise and vibrations. Efforts will be made to minimize disruption.
- Transit: Transit along Crowchild Tr N.W. may be impacted by ramp closures. Visit calgarytransit.com for more information.
About the project
As part of the Annual Paving Program, The City of Calgary will begin road maintenance on Crowchild Trail N.W., from Stoney Trail N.W. to 32 Ave N.W. This construction work is essential to ensure the safety and longevity of our roads and sidewalks, helping to prevent more costly and disruptive reconstruction in the future. This year’s scope of work includes asphalt roadway repair and replacement, as well as localized concrete repair and replacement of sidewalks, wheelchair ramps, curbs, barriers, and gutters.
Budget
The construction cost is $7.3 million, which is part of the $40 million Annual Paving Program budget for 2024. It’s important to note that this project will not only improve pavement quality on Crowchild Trail N.W. but also replace sidewalks and wheelchair ramps to improve safety and accessibility for pedestrians and other users.